1. Design basis
"Environmental Protection Law of the People's Republic of China"
"Water Pollution Prevention and Control Law of the People's Republic of China"
"Construction Project Environmental Protection Design Regulations"
"Emission Standard of Pollutants for Urban Sewage Treatment Plants"(GB18978-2002)
"Code for Design of Pipeline Structure for Water Supply and Drainage Engineering" GB 50332-2002
"Technical Specifications for Safety Protection Engineering" GB 50348-2004
"Design Specifications for Noise Control in Industrial Enterprises" GBJ 87-85
2. Design parameters and design conditions
This project is designed according to the typical municipal sewage influent quality, as shown in Table 1:
Table 1 Design influent water quality
| Serial number | Index | Design influent water quality |
| 1 | Chemical oxygen demand CODcr (mg/L) | 90 |
| 2 | 5-day biochemical oxygen demand BOD5 (mg/L) | 45 |
| 3 | Suspended solids SS (mg/L) | 25 |
| 4 | Ammonia nitrogen NH4+-N (mg/L) | 46 |
| 5 | Total nitrogen TN (mg/L) | 48 |
| 6 | Total Phosphorus TP (mg/L) | 5.0 |
| 7 | PH | 6~9 |
| 8 | Water temperature | 8℃~25℃ |
The plan takes the A standard of the first-level standard in the "Pollutant Discharge Standard for Urban Sewage Treatment Plants" (GB18978-2002) as the basic requirements, and according to other reuse purposes, at the same time follows the "Water Quality of Urban Sewage Recycling and Utilization Landscape Environment Water Quality" (GB/ T18921-2002) standard for water quality for ornamental river landscape environment and the "Water Quality for Urban Wastewater Recycling and Utilization" (GB/T18920-2002) standard, the effluent water quality standard takes the strictest value among the above standards, as shown in Table 2 below :
Table 2 Design effluent quality
| Serial number | Index | Level A | Landscape water quality | Miscellaneous water quality | Design value |
| 1 | Chemical oxygen demand CODcr (mg/L) | ≤50 | / | / | ≤50 |
| 2 | 5-day biochemical oxygen demand BOD5 (mg/L) | ≤10 | ≤10 | ≤10 | ≤10 |
| 3 | Suspended solids SS (mg/L) | ≤10 | ≤20 | / | ≤10 |
| 4 | Ammonia nitrogen NH4+-N (mg/L) | ≤5 | ≤5 | ≤10 | ≤5 |
| 5 | Total nitrogen TN (mg/L) | ≤15 | ≤15 | / | ≤15 |
| 6 | Total Phosphorus TP (mg/L) | ≤0.5 | ≤1 | / | ≤0.5 |
| 7 | pH value | 6~9 | 6~9 | 6~9 | 6.5~8.5 |
3. Design range and water volume
The design water volume of this project is 200m³/d or 8.3m³/h
4. Main sewage treatment methods and recommended sewage treatment process
4.1 Introduction of processing methods
Wastewater treatment can be divided into three categories:
1)Physical treatment;
2)chemical treatment;
3)Biochemical treatment method
a、Physical treatment
Physical treatment refers to a treatment method that uses physical action to change the composition of wastewater.
Common physical treatment methods include sedimentation, air flotation, filtration, and microfiltration. The first two processes are mostly used for pretreatment or primary treatment, and the latter two are mainly used for advanced treatment.
b、Chemical treatment
The chemical treatment method refers to the application of chemical principles and chemical action to convert the pollutant components in the wastewater into harmless substances, so that the wastewater can be purified.
Contaminants change their chemical nature after chemical treatment processes, which are always accompanied by chemical changes. The chemical treatment methods of food industry wastewater include neutralization, coagulation, electrolysis, redox, ion exchange, membrane separation, etc.
c、Biochemical treatment
Biochemical treatment is one of the most important processes in organic wastewater treatment systems.
In wastewater treatment, biological treatment process can be divided into aerobic process, anaerobic process, stabilization pond, land treatment and various combined processes formed by the combination of the above processes. Biological method is the main secondary treatment process, the purpose is to degrade COD, BOD5, ammonia nitrogen and total phosphorus.
The selection of sewage treatment process should fully consider the volume and quality of sewage, economic conditions and management level, and give priority to mature processes with reasonable and advanced technology, safety and reliability, low energy consumption, low investment, less land occupation and convenient operation and management. The characteristics of each process are discussed below in order to select a practical solution.
4.2 Recommended treatment process
According to the target situation of sewage influent water quality and effluent water quality, comprehensively considering factors such as reliability, maturity, applicability, efficiency of pollutant removal, low investment, simple operation and management, low operating cost and on-site conditions, the final decision is made. The anaerobic + anoxic + aerobic + MBR (membrane bioreactor) process is selected with stable and reliable effluent, advanced technology, small footprint and convenient operation and management.
Membrane bioreactor (MBR) is a new wastewater treatment process produced by the organic combination of membrane technology and sewage biological treatment technology. The feature of this technology is that the low-pressure membrane separation process replaces the gravity sedimentation separation process in the traditional activated sludge treatment process, so that the hydraulic retention time and the sludge age are completely separated, and the biomass in the reactor is effectively preserved, so that the biological treatment process can be Removing more than 95% of COD and about 90% of denitrification effect:
Meijiejing membrane bioreactor technology has many obvious advantages that other biological treatment processes cannot match. Compared with other biological treatment processes, membrane bioreactors have the following characteristics:
► Small footprint, about 1/2~1/5 of the traditional craftsmanship;
► Can completely remove suspended substances in water;
► The effluent can be reused to truly achieve zero discharge of sewage (depending on the specific situation and related to the quality of the influent);
► COD, solids and nutrients can be removed in one unit;
► High load rate, up to 2~5KgCOD/m³.d
► Low sludge yield, 10~30% of conventional methods;
► The process starts quickly;
► The system is not affected by sludge bulking;
► The effluent quality is good and stable.
5. Design process flow
Schematic diagram of the process flow of the sewage treatment plant
6. The design features of this project
Considering the simplification of civil construction conditions and the reduction of construction difficulty, this project is designed as a modular system.
This equipment has the following features:
1. The quality of the effluent is good, and the suspended solids and turbidity of the effluent are close to zero, which can be directly reused, realizing the recycling of sewage.
2. The efficient interception of the membrane makes the operation control more flexible and stable.
3. The system can realize fully automatic control.
4. Small footprint and centralized process equipment.
Fields of application of this system:
1. Areas or places where sewage is reused, such as hotels, car washes, public toilets, etc. This system has the characteristics of small footprint, compact equipment, automatic control, flexibility and convenience.
2. Apply to areas without drainage pipe network, such as small settlements, resorts, tourist scenic spots, etc.
3. Applied to the treatment of high-concentration organic wastewater. For example, high-concentration organic wastewater is a common point pollution. The national food, pharmaceutical, aquaculture wastewater and other industries discharge a large amount of high-concentration organic wastewater every year.
7. Process flow design description:
The sewage source water is filtered through the basket grill to filter out the large particles. Self-flowing to the regulating tank, through the lifting pump to the biochemical tank, the activated sludge microorganisms, nitrifying bacteria and phosphorus bacteria that multiply in aeration state degrade or absorb organic pollutants containing carbon, ammonia nitrogen and phosphorus in the water. The MBR effluent membrane adopts the high-quality PVDF membrane of our company's cooperative unit. In this project, the membrane water flux adopts 10-15L/㎡.h. The membrane is installed on a special stainless steel frame, which is an integral installation, maintenance and maintenance unit. The chemical cleaning of the MBR membrane is to clean the membrane module when the MBR runs for a period of time (the specific time should be determined according to the water quality of the influent and the operation of the equipment). Inject the prepared liquid (acid or sodium hypochlorite) into the membrane tank to be cleaned, soak for 30 minutes, and inject a certain amount of air to purge to fully remove the pollutants attached to the membrane module. Each chemical cleaning is not Both of the above two liquids are required to be soaked, but it depends on the operation of the MBR. The cleaning liquid in the membrane tank can be measured regularly and quantitatively, and the liquid concentration in the tank can be automatically controlled by the sodium hypochlorite dosing pump and the liquid level control device in the tank.
In this project, the MBR membrane tank is placed behind the biochemical tank, and the sewage from the aerobic tank is filtered into the membrane tank through gravity flow. The circulation of sludge is beneficial to the metabolism of activated sludge.
When MBR membrane is installed, maintained and maintained, it is based on the entire membrane frame and membrane.
The operation of MBR pool effluent, variable frequency reuse water pump, chemical cleaning and other operations are realized through PLC automatic control.
AUTOMATIC CONTROL DESIGN
1. Design basis
The design of the automatic control instrument is based on the process recommendation scheme and the requirements of the process for the automatic control system, combined with the characteristics of the automatic control instrument industry.
The relevant design specifications are as follows:
"Automation Instrument Selection Regulations"(HG/T20507-2000)
"Instrument piping and wiring design regulations"(HG/T20512-2000)
"Instrument System Grounding Design Regulations"(HG/T20513-2000)
"Control Room Design Regulations"(HG/T20508-2000)
"Instrument Power Supply Design Regulations"(HG/T20509-2000)
2. Description of automatic control system
The automatic control system scheme of this project is formulated according to the technological process and technological characteristics. Based on the actual situation of the project and process requirements, the design adopts the current advanced and mature distributed control system. It integrates computer technology, control technology, communication technology and display technology, and the on-site PLC sub-stations are connected to realize centralized monitoring management and decentralized control. In this way, the defects of centralized control system such as concentration of risk, poor reliability, difficult expansion and large amount of control cables are overcome, and the centralization of information, scheduling and management and the dispersion of functions and control risks are realized. The on-site PLC sub-stations can work independently and stably, which fundamentally improves the system reliability. The cost-effectiveness of the distribution system with PLC as the main body is relatively high. It mainly has the following characteristics:
1. Improve the utilization rate of equipment and ensure the quality of water treatment. Through the instruments installed on site, various process parameters can be continuously monitored. According to these parameters, the automatic control system can coordinate the relationship between the water treatment processes in each section to ensure the full utilization of equipment. And according to the data detected by the instrument, the deviation is corrected in time to ensure the quality of sewage treatment.
2. To ensure the reliable operation of the system, due to the installation of corresponding water quality monitoring instruments in each process section, the operating parameters and operating status of each equipment, equipment failures can be found at any time, and alarms will be issued in time.
3. Due to the implementation of computer optimization control, daily operating costs are saved and sewage treatment costs are reduced.
4. Save manpower and reduce labor intensity.
3. On-site testing instruments
Field detection instruments are an indispensable part of computer system control, and the quality of instrument selection directly affects the reliability of the control system. Taking into account the adaptability of the working environment, especially the sensor is in direct contact with water and other media, it is very easy to corrode and smear. Therefore, the sensor parameters are non-diaphragm, non-contact and easy-to-clean. Taking into account the ease and convenience of maintenance and management, the instrument with continuous flow disassembly and long maintenance period should be selected as much as possible.
All instruments use intelligent instruments with on-site display transmitters, and have 4-20mA DC output, and the signals are transmitted to the PLC through the communication network.
(1)Liquid level detection instrument:
Adopt ultrasonic level gauge and electric contact type level gauge
(2)Flow detection instrument:
The flowmeter in the pipeline should use an electromagnetic flowmeter.
(3)Pressure detection instrument:
The pressure sensor in the pipeline with sludge adopts the anti-clogging diaphragm sensor.
(4)Product water turbidity detection instrument:
A stable E+H turbidimeter is used.
All instruments use intelligent instruments with on-site display transmitters, and with 4-20mA DC output, the signals are transmitted to the monitoring computer through the on-site terminal and communication network, and displayed on the computer display terminal.
OPERATION SERVICE
1. Quality warranty period
During the operation period, it is responsible for the comprehensive quality guarantee responsibility of the system, and the quality commitment: guarantees that the continuous outage time of the equipment during continuous operation shall not exceed 48 hours.
2. Operational services provided
According to the scale of project equipment, we provide on-site/24-hour remote supervision to operate and maintain rental equipment. For remote hosting projects, the number of on-site inspections is not less than once per quarter.
Provide complete equipment and necessary data for environmental protection monitoring every month, complete data collection and uploading, and complete the environmental protection ledger record of management equipment.
Ensure that the continuous discharge of equipment meets the standards, and deal with unqualified discharges within the scope of water quality commitments as agreed in the contract, and bear corresponding social responsibilities such as environmental protection fines.